Now, here is the hubiC roadmap updated :

Done those last two weeks :
- Infrastructure : Correct frequent errors 500 on the application

ETA 3 days :
- Apps: Resolve publication feature problems

ETA 10 days :
- Apps/infra : Optimize infrastructure configuration to diminish « timeout »

ETA 20 days :
- Nothing To Report

No ETA :
- Infrastructure : Bug created by “rename” function (we will precise the ETA on the problem is known)
- Infrastructure : Migrate Roubaix and Strasbourg infrastructure to Gravelines Datacenter (The task is currently happening but it is a long term project)
- Apps : Delete a voluminous backup (we will precise the ETA on the problem is known)
- Apps : Optimize password changes on Android application
- Apps : Save login information on Android application
- Apps : Bugfix of the upload for Android application
- Apps : Optimize the expiration password process on Android application
- Billing : Quota of the offer corrected after an unpaid event on your ADSL access

We will adapt this roadmap according to the evolutions of the service and to the feedbacks you will give us.

Regards,

The hubiC team

BenoitH
06-15-2016, 05:51 PM
Hello everyone,

Last week I forgot to push the update of the roadmap. My apologies for the mistake, I’ll correct my mistake right away.

This week and for several days before, all our effort have been oriented toward the correction of “500 errors” that have been multiplying over the last few weeks. We think we have found a solution to the problem. Tomorrow morning we will push under production this bugfix. We could help your feedback on this mailing list to confirm the efficacity of this bugfix tomorrow afternoon.

Now, here is the hubiC roadmap updated :

Done those last two weeks :
- Billing: Give access to billing interface for suspended account - allow them to regularize their situation
- Apps : bugfix HTTP 408 on file creation
- Apps: release of new version of svfs 0.7 (https://github.com/ovh/svfs/releases)
- Apps : Deadlock when changing attributes on freshly created file
- Gateway : Provisionning of Docker infrastructure for the gateway beta (Rsync/SCP/SFTP over fuse)
- Infrastructure : Bugfix error on Thumbnails generation (Miniature on the webapp)
- Infrastructure : Diagnosis and bugfix hubiC instability on Orange network (The problem is due to a deprecated version of the Orange’s livebox. If you encounter this problem please reboot your Orange’s livebox and update it)
- Infrastructure : 10Mbps bandwidth limitation

ETA 3 days :
- Infrastructure : Correct frequent errors 500 on the application

ETA 10 days :
- Nothing To Report

ETA 20 days :
- Nothing To Report

No ETA :
- Apps : Delete a voluminous backup (we will precise the ETA on the problem is known)
- Apps : Optimize password changes on Android application
- Apps : Save login information on Android application
- Apps : Bugfix of the upload for Android application
- Apps : Optimize the expiration password process on Android application
- Infrastructure : Migrate Roubaix and Strasbourg infrastructure to Graveline Datacenter (The task is currently happening but it is a long term project)
- Apps: Resolve publication feature problems
- Billing : Quota of the offer corrected after an unpaid event on your ADSL access

We will adapt this roadmap according to the evolutions of the service and to the feedbacks you will give us.

Regards,

The hubiC team

BenoitH
06-01-2016, 07:15 PM
Hello everyone,

Like every week, you will find below the hubiC roadmap updated :

ETA 3 days :
- Billing: Give access to billing interface for suspended account - allow them to regularize their situation (The quality check of this feature took longer than expected, we hope to push it on production this week)
- Billing : Quota of the offer corrected after an unpaid event on your ADSL access
- Infrastructure : Diagnosis and bugfix hubiC instability on Orange network (We think we have identified the origin of the problem, we will communicate the bugfix this week)
- Apps: Resolve publication feature problems
- Apps : bugfix HTTP 408 on file creation
- Apps : Deadlock when changing attributes on freshly created file

ETA 10 days :
- Gateway : Provisionning of Docker infrastructure for the gateway beta (Rsync/SCP/SFTP over fuse)

ETA 20 days :
- Billing : Resolve issues met on partners commercial offers
- Infrastructure : 10Mbps bandwidth limitation
- Gateway : Release of Gateway Beta (Rsync/SCP/SFTP over fuse)

No ETA :
- Infrastructure : Bugfix error on Thumbnails generation
- Infrastructure : Correct frequent errors 500 on the application (We continue to optimize the “rebalance” process, and investigate on the other sources of 500 errors)
- Apps : Delete a voluminous backup (we will precise the ETA on the problem is known)
- Apps : Optimize password changes on Android application
- Apps : Save login information on Android application
- Apps : Bugfix of the upload for Android application
- Apps : Optimize the expiration password process on Android application
- Infrastructure : Migrate Roubaix and Strasbourg infrastructure to Graveline Datacenter (The task is currently happening but it is a long term project)
We will adapt this roadmap according to the evolutions of the service and to the feedbacks you will give us.

Regards,

The hubiC team

BenoitH
05-25-2016, 05:57 PM
Hello everyone,

This week we reorganized our roadmap so that we can release new transfer protocols rsync/SCP/SFTP over fuse, and the PCA beta offer, at the end of June 2016.
Consequently, we removed some billing elements from our roadmap et delayed some of the bugfix.

We also grouped some elements of the gateway project to present only two elements on the roadmap (provisioning infrastructure for the beta in 10 days, release the beta in 20 days)

Like every week, you will find below the hubiC roadmap updated :

Task prodded lately :
- Billing : Bugfix hubiC order problem for customer who resiliated their ADSL account recently
- Gateway : upgrade svfs (version 6.1)
- Gateway : Support for symlinks on svfs (https://github.com/ovh/svfs/issues/62)

ETA 3 days :
- Billing: Give access to billing interface for suspended account - allow them to regularize their situation
- Infrastructure: Diagnosis of the origin of errors 500 (To ensure that Erasure coding is the only source of errors 500)

ETA 10 days :
- Facturation : Quota of the offer corrected after an unpaid event on your ADSL access
- Apps: Resolve publication feature problems
- Gateway : Provisionning of Docker infrastructure for the gateway beta (Rsync/SCP/SFTP over fuse)

ETA 20 days :
- Billing : Resolve issues met on partners commercial offers
- Infrastructure : Migrate Roubaix and Strasbourg infrastructure to Graveline Datacenter
- Infrastructure : 10Mbps bandwidth limitation
- Gateway : Release of Gateway Beta (Rsync/SCP/SFTP over fuse)

No ETA :
- Infrastructure : Bugfix error on Thumbnails generation
- Infrastructure : Diagnosis and bugfix hubiC instability on Orange network
- Infrastructure : Correct frequent errors 500 on the application ( we will precise the ETA on the problem is known)
- Apps : Delete a voluminous backup ( we will precise the ETA on the problem is known)

We will adapt this roadmap according to the evolutions of the service and to the feedbacks you will give us.

Regards,

the hubiC team

BenoitH
05-18-2016, 06:31 PM
Hello everyone,

The month of May, with all its vacation time, slows our developments. We had to review several ETA because of those vacation time
Like every week, you will find below the hubiC roadmap of the week :

Task prodded lately :
- Billing : Rectify billing process - Automatically reopen an account after regularization of an unpaid bill
- Billing: Handling several credit card per user
- Apps : Support for encryption in svfs
- Apps : OSX packaging for hubiC new protocoles
- Apps : Affichage du quota d’utilisation du filesystem svfs
- Apps : Display usage quota of the svfs filesystem
- Infrastructure : Migrate Swift version to 2.7 (Openstack Mitaka) on Hubic infras
- Infrastructure : Bugfix of SSL problem on SFR fiber customers
- Infrastructure : Performance Benchmark of different Swift filesystems (We confirmed that our filesystem was the most optimized for our usage)
- Gateway : Creation of a docker image for new hubiC gateways
- Gateway : Creation of PAM scripts

ETA 3 days :
- Billing: Give access to billing interface for suspended account - allow them to regularize their situation
- Billing : Bugfix hubiC order problem for customer who resiliated their ADSL account recently

ETA 10 days :
- Billing: Manage prorata when a customer change his offer
- Billing: Migration of xDSL account
- Billing: Bugfix the billing calculation when customer upgrade his offer
- Apps: Resolve publication feature problems
- Infrastructure : Performance Benchmark of different Swift filesystems
- Gateway : Create CDS pipelines

ETA 20 days :
- Billing : Bugfix prorata problem when upgrading/downgrading an offer
- Billing : Resolve issues met on partners commercial offers
- Infrastructure : Migrate Roubaix and Strasbourg infrastructure to Graveline Datacenter
- Infrastructure : 10Mbps bandwidth limitation
- Gateway : Scaling up the number of containers

No ETA :
- Infrastructure : Bugfix error on Thumbnails generation
- Gateway : Order and configure IPLBs
- Infrastructure : Diagnosis and bugfix hubiC instability on Orange network ( we will precise the ETA on the problem is known)

We will adapt this roadmap according to the evolutions of the service and to the feedbacks you will give us.

Regards,

the hubiC team

BenoitH
05-04-2016, 07:03 PM
Hi everyone,

We wish to keep you inform of our latest developments on hubiC product and to give you more visibility on the product future.

You will find below the first draft of our roadmap which currently focus on three points : Billing, transfer protocols (Gateways) and Infrastructure.

We have given ourselves the objective to updates and optimize this roadmap every Wednesday on the mailing list and on the forum.
We hope it will clarify the way the product evolve.

Task prodded lately :

- Billing : Bug fix account creation process – New account stuck in status "creating"
- Billing : Rectify billing process - Automatically reopen an account after regularization of an unpaid bill
- Apps : Support for encryption in svfs
- Infrastructure : Migrate Swift version to 2.7 (Openstack Mitaka) on Hubic infras
- Infrastructure : Migrate hubic.com load balancer from ACE to IPLB
- Gateway : Creation of a docker image for new hubiC gateways
- Gateway : Creation of PAM scripts
- Gateway : Patch openssh in order to make sftp usable with svfs

Short term tasks :

- Billing: Give access to billing interface for suspended account - allow them to regularize their situation
- Billing: Handling several credit card per user
- Billing: Bugfix hubiC quota after an ADSL unpaid event
- Billing: Warn customer when his credit card expire
- Infrastructure : 1 swift process per port and per disk

Medium term tasks:

- Billing: Manage prorata when a customer change his offer
- Billing: Migration of xDSL account
- Billing: Bugfix the billing calculation when customer upgrade his offer
- Infrastructure : Performance Benchmark of different Swift filesystems
- Infrastructure : 10Mbps bandwidth limitation
- Gateway : Order and configure IPLBs
- Gateway : Create CDS pipelines

Long term tasks :

- Facturation : Gestion du prorata suite à une migration d’offre
- Infrastructure : Diagnosis and bugfix hubiC instability on Orange network
- Infrastructure : Migrate Roubaix and Strasbourg infrastructure to Graveline Datacenter
- Infrastructure : Bugfuix error on Thumbnails generation
- Gateway : Scaling up the number of containers